I am in Phoenix, AZ, USA and I am planning a solar self-install on my roof using Enphase microinverters with a grid tie installation of 6.2-6.6 KW.
My utility (APS) requires that I install both a Solar meter and a disconnect. I'm trying to figure the specifics of my system and have a few questions.
To start off, I want to say that I know it is ultimately up to the exact conditions of my home and the opinion of the AHJ whether or not something is acceptable and meets code. Also, when it comes to actually working on the Main SES, I will hire an electrician, but I want to understand what is being done and not make unnecessary changes.
All that said, my questions are:
1. I have a 200A main panel. If my backfed breaker is 40A, do I need to derate the main? My understanding is that NEC says that I can install up to 120% of of the Main rating so it looks like 40A is acceptable with no derate.
2. If AC amps from the microinverters is 32A or less, is a 40A breaker at the main sufficient? (note: I am only planning for 23-28 amps)
3. If I have OCPDs (2 20A breakers) on the roof in a combiner box, do I need another sub panel? or can I just wire direct from the combiner box to the PV meter? If I can, is it okay to transition from the 12 AWG wire in the engage cable to 6AWG romex/NM-B for the run to the PV Meter.
4. Does anyone know if the GE kv2cs meter is acceptable to APS as a PV meter?
5. Last question, It appears from reading APS's documentation that my disconnect needs to be at least a 2p 60A nonfusable. Would a D Square DU222RB meet that criteria? If it does, is it sufficient for my service, or do I somehow need larger because of the larger SES main size?
Thank you in advance for you assistance..
My utility (APS) requires that I install both a Solar meter and a disconnect. I'm trying to figure the specifics of my system and have a few questions.
To start off, I want to say that I know it is ultimately up to the exact conditions of my home and the opinion of the AHJ whether or not something is acceptable and meets code. Also, when it comes to actually working on the Main SES, I will hire an electrician, but I want to understand what is being done and not make unnecessary changes.
All that said, my questions are:
1. I have a 200A main panel. If my backfed breaker is 40A, do I need to derate the main? My understanding is that NEC says that I can install up to 120% of of the Main rating so it looks like 40A is acceptable with no derate.
2. If AC amps from the microinverters is 32A or less, is a 40A breaker at the main sufficient? (note: I am only planning for 23-28 amps)
3. If I have OCPDs (2 20A breakers) on the roof in a combiner box, do I need another sub panel? or can I just wire direct from the combiner box to the PV meter? If I can, is it okay to transition from the 12 AWG wire in the engage cable to 6AWG romex/NM-B for the run to the PV Meter.
4. Does anyone know if the GE kv2cs meter is acceptable to APS as a PV meter?
5. Last question, It appears from reading APS's documentation that my disconnect needs to be at least a 2p 60A nonfusable. Would a D Square DU222RB meet that criteria? If it does, is it sufficient for my service, or do I somehow need larger because of the larger SES main size?
Thank you in advance for you assistance..
Comment